Rooftop solar in Meghalaya

The short answer

A 3 kW system in Meghalaya costs about ₹1,74,000 before subsidy and ₹88,200 after the ₹85,800 PM Surya Ghar subsidy. Against MePDCL’s average of ₹6.1/unit, it saves around ₹1,775 a month and breaks even in roughly 4.1 years.

avg tariff, ₹/unit
₹6.1
avg tariff, ₹/unit
units per kW monthly
97
units per kW monthly
max central subsidy
₹85,800
max central subsidy

Meghalaya: Special-category CFA applies here — ₹85,800 at 3 kW instead of ₹78,000. Shillong's generation is among the lowest in the country (about 97 units per kW per month) and its tariff is below the national average, so the subsidy, not the savings, is what makes the payback work.

System prices in Meghalaya, after subsidy

At the live ₹58,000/kW benchmark. Your signed quote should be within about 15% of these figures — ask for the difference line by line.

SystemBefore subsidySubsidyNet costSaves/monthPayback
1 kW₹58,000−₹33,000₹25,000₹5924 yrs
2 kW₹1,16,000−₹66,000₹50,000₹1,1834 yrs
3 kW₹1,74,000−₹85,800₹88,200₹1,7754 yrs
5 kW₹2,90,000−₹85,800₹2,04,200₹2,9596 yrs
10 kW₹5,80,000−₹85,800₹4,94,200₹5,9177 yrs

Savings assume the system offsets your consumption via MePDCL net metering.

What each size needs and produces in Meghalaya

Output is 97 units per kW per month — Meghalaya’s own figure, not a national average — so a system here generates about 1164 units per kW over the year. Roof area assumes 90 sq ft of shadow-free space per kW.

SystemRoof neededUnits/monthUnits/yearSizing guide
1 kW90 sq ft9711641 kW guide
2 kW180 sq ft19423282 kW guide
3 kW270 sq ft29134923 kW guide
5 kW450 sq ft48558205 kW guide
10 kW900 sq ft9701164010 kW guide

Annual output is the monthly figure × 12, so it assumes average weather. The weakest month is roughly 25% below the average — worth knowing before you size a system against a summer bill.

Meghalaya solar FAQ

What is the solar subsidy in Meghalaya?

Meghalaya homes get the central PM Surya Ghar subsidy: ₹33,000/kW up to 2 kW, capped at ₹85,800 for 3 kW and larger systems. It is credited to your bank account after MePDCL commissions the system — not adjusted by the installer.

How many units does 1 kW generate in Meghalaya?

About 97 units a month — roughly 3.2 units a day — varying with season, orientation and shading.

Which DISCOM handles rooftop solar in Meghalaya?

MePDCL processes the net-metering application, the feasibility check and the bidirectional meter for residential systems.

Is rooftop solar worth it in Meghalaya?

At ₹6.1/unit and 97 units per kW monthly, households with bills above ₹2,000–3,000 usually break even in 3–5 years — then draw near-free power for the remaining 20-plus years of panel life.